EVMS for TOF Construction

Spoke with Phil Kessler on 9/12/2012

  • usually reports are done monthly
  • needs to be done by September: cost incurred in the past cannot be moved and some are ending in September
  • just percentages no good for reporting progress
  • progress can be claimed for items scheduled for future months

Questions:

  • Does this consitute a change request?
  • What costs have already been booked?
  • What costs have been claimed?